This document presents the technical layout and the cost assessment for the infrastructure of the PANDA experiment, comprising the following major items:
- Supports: Mechanical structures to support the experimental setup, fixed and removable platforms to house equipment and to assemble the experiment, including staircases, ladders,fences, racks and related tools.
- Supplies: Distribution systems for electrical power, grounding, fluids and gases.
Based on this, the current integration planning and the installation procedure are described.
UPDATE July 3: Updated version v1.0 submitted to external referees.
UPDATE August 28: Updated version v2.0 for inspection by the PANDA CB before submission to ECE.
UPDATE September 14: Version v3.0 for submission to FAIR ECE. Bibliographies completed.
- Supports: Mechanical structures to support the experimental setup, fixed and removable platforms to house equipment and to assemble the experiment, including staircases, ladders,fences, racks and related tools.
- Supplies: Distribution systems for electrical power, grounding, fluids and gases.
Based on this, the current integration planning and the installation procedure are described.
UPDATE July 3: Updated version v1.0 submitted to external referees.
UPDATE August 28: Updated version v2.0 for inspection by the PANDA CB before submission to ECE.
UPDATE September 14: Version v3.0 for submission to FAIR ECE. Bibliographies completed.